Turlock Irrigation District - Modesto Irrigation District
LA GRANGE HYDROELECTRIC PROJECT
FERC NO. 14581

Integrated Licensing Process Timeline

  • January 29, 2014:  Districts File Pre-Application Document (PAD)
  • FERC conducts scoping
    • May 23, 2014: FERC issues Scoping Document 1 (SD1)
    • June 18-19, 2014: FERC holds site visit and public scoping meetings
    • September 5, 2014: FERC issues Scoping Document 2 (SD2)
  • September 5, 2014:  Districts file Proposed Study Plan (PSP)
  • January 5, 2015:  Districts file Revised Study Plan (RSP)
  • February 2, 2015:  FERC issues its Study Plan Determination (SPD)
  • May 1, 2015:  FERC Director issues Study Dispute Determination (SDD)
  • February 2, 2016:  Districts issue Initial Study Report (ISR)
  • February 1, 2017:  Districts issue Updated Study Report (USR)
  • April 24, 2017:  Districts file Draft License Application (DLA)
  • October 11, 2017:  Districts file Final License Application (FLA)
  • February 11, 2019:  FERC issues Draft Environmental Impact Statement (DEIS)
  • July 7, 2020:  FERC issues Final Environmental Impact Statement (FEIS)
  • Future Date:  FERC issues new license with new terms and conditions